A55 J27 Talardy Interchange Bridges 7/09/2020 – 27/11/2020

4 weeks A55 Lane closures Monday to Friday from 27th September

2 weeks A55 night time closures 20:00-06:00

Where and Why?

Work to carry out repairs and strengthening to the ends of the bridges of Talardy Interchange.

  • Lane closures are needed on A55 whilst work is carried out below.  Westbound carriageway lane closures at J27 Talardy Interchange Bridges will commence on the 27/09/2020 for 4 weeks.  Lane closures will commence each week at 23:00 Sunday until 10:00 Friday.
  • Lane closures are needed on A55 whilst work is carried out below.  Eastbound carriageway lane closures at J27 Talardy Interchange Bridges will commence on the 27/09/2020 for 4 weeks.  Lane closures will commence each week at 23:00 Sunday until 23:59 Friday.
  • Sliproad closures are needed at J27 whilst work is carried out below.  Eastbound On-slip full closures will commence on the 24/9/2020 for two days then from 4/10/2020 until the 13/11/2020.  Slip road closures will commence each week at 23:00 Sunday until 23:59 Friday.  
  • Sliproad closures are needed at J27 whilst work is carried out below.  Westbound Off-slip full closures will commence on the 11/10/2020 until the 13/11/2020. Slip road closures will commence at 23:00 Sunday until 23:59 Friday. *
  • Lane closures are needed at Talardy Interchange Roundabout whilst work is carried out at the ends of the bridges. Roundabout Lanes will be restricted to 1 Lane commencing on the 28/09/2020 until the 22/10/2020.

Work to carry out replacement of bridge deck expansion joints and re-surface the carriageway over the bridges

  • Closure of the  A55 Eastbound carriageway at J27 Talardy Interchange Bridges and on the J27 eastbound on-slip will commence on the 08/11/2020 for 10 nights. Closures will commence at 20:00 until 06:00 each night.
  • Closure of the A55 Westbound carriageway at J27 Talardy Interchange Bridges and on the J27 westbound off-slip will commence on the 8/11/2020 for 10 nights. Closures will commence at 20:00 until 06:00 each night.
     

*Note, closures will not be in place 25/10/2020-6/11/2020 to avoid half-term holiday traffic.


Diversions and Safety Measures

The works are being carried out after the summer holiday period when traffic flows have reduced and are programmed to avoid busier weekend periods. Traffic will be diverted on the A55 via J26 during slip road closures.  


Resurfacing and Joint Replacement requiring full A55 carriageway closures are programmed to be carried out overnight when traffic flows are lower to minimise disruption.


Proposed programme of traffic management restrictions:

Details of Restriction

Start Date and Time**

End Date and Time**

Notes

 

Single lane closures of A55 Westbound carriageways through J27.

27/09/2020

23:00

02/10/2020

10:00

Full time

 

04/10/2020

23:00

09/10/2020

10:00

 

11/10/2020

23:00

16/10/2020

10:00

 

18/10/2020

23:00

22/10/2020

10:00

 

Full Closure of A55 Westbound carriageways through J27.

08/11/2020

20:00

17/11/2020

06:00

Night time only*

 

Single lane closures of A55 East bound carriageways through J27.

27/09/2020

23:00

02/10/2020

23:59

Full time

 

04/10/2020

23:00

09/10/2020

23:59

 

11/10/2020

23:00

16/10/2020

23:59

 

18/10/2020

23:00

23/10/2020

23:59

 

Full Closure of A55 East bound carriageways through J27.

08/11/2020

20:00

17/11/2020

06:00

Night time only*

 

Full Closure of A55 J27 Eastbound on Slip.

24/09/2020

06:00

25/09/2020

23:59

Full time*

 

04/10/2020

23:00

09/10/2020

23:59

 

11/10/2020

23:00

16/10/2020

23:59

 

18/10/2020

23:00

23/10/2020

23:59

 

28/10/2020

07:00

06/11/2020

17:00

 

08/11/2020

23:00

13/11/2020

23:59

 

Full Closure of A55 J27 Westbound off Slip.

11/10/2020

23:00

16/10/2020

23:59

Full time*

 

18/10/2020

23:00

23/10/2020

23:59

 

08/11/2020

23:00

13/11/2020

23:59

 

A525 Circulatory Carriageway at Talardy Interchange (J27 A55) reduced to 1 lane.

28/09/2020

08:00

22/10/2020

10:00

Full time

 
 
 

 

*The slip roads and the main carriageway will not be closed at the same time.
** dates provisional, may be subject to change
 