Start Date: 16/05/22 | End Date: 05/08/22
Work to improve the strength of the A470 Caersws Bridge structure will take place over 12 weeks.
Work to undertake essential Strengthening Works will commence on the 16/05/2022 for approximately 12 weeks.
The current restrictions will remain in place until completion of the work.
The contractors will utilise the existing traffic management system currently in place over the bridge (traffic signals).
On completion of the works these signals will be removed and the bridge will be reopened to normal traffic operation.
Should there be a requirement for any night time full closures of the bridge, these will be notified separately.
For further information, please contact Traffic Wales on 0300 123 1213 or via Twitter @TrafficWalesN