A494 Drome Corner to Queensferry Interchange: River Dee Bridge crossover and junction improvement works

Start date: 04/06/24 - End date: 13/07/24 

Picture of the A494

Work to carry out installation of two crossover points in the central reserve and small improvements to the Riverside junction on the westbound carriageway, between Drome Corner and Queensferry Interchange. Work will commence on the 04/06/2024. 

The work will be carried out overnight from 20:00 – 06:00 under two lane 2 closures both westbound and eastbound. A lane 1 closure will be in place on the westbound carriageway to accommodate for junction improvement works.

There will be a 30mph speed restriction throughout the site 24/7 as mitigation for the barrier works taking place.

The works are being carried out overnight when traffic flows are lower to minimise disruption.

4 June – 2 July 

•    Lane 2 closures A494 Drome Corner to Queensferry Interchange both directions from 20:00-06:00.

2 – 10 July

•    Lane 1 closure westbound Drome Corner to Queensferry Interchange from 20:00-06:00.

11 – 13 July

•    Lane 2 closures A494 Drome Corner to Queensferry Interchange both directions from 20:00-06:00.

Diversion not required for these works.