Start date: 08/09/23 | End date: 4/12/23
Essential maintenance work to M4 River Usk Bridge (mainly J26 Malpas)
There will be overnight closures and day closures during the main works as detailed below.
Weekend Closure:*
2 December, 20:00 - 3 December, 10:00:
Closure of the eastbound off-slip at Junction 26 (Malpas). Traffic will be diverted from Junctions 26 to 24 (Coldra Interchange).
3 December, 20:00 - 4 December 06:00:
Closure of the eastbound off-slip at Junction 26 (Malpas). Traffic will be diverted from Junctions 26 to 24 (Coldra Interchange).
*These dates are subject to weather and may have to be changed if the conditions are unfavourable.
For slip-road closures, the following diversion will be in place:
For information relating to Traffic Management, please contact Costain
on 07818 597724. This number is open 24hrs.
For all other queries, contact Traffic Wales on 0300 123 1213 or via X @TrafficWalesS and Facebook @TrafficWalesS.