M4 Hazard Tree Clearance and Vegetation Maintenance between the Second Severn Crossing and Pont Abraham

Start: Autumn 2026 | End: Spring 2027

M4 Trees growing

Essential works to address hazardous trees at various locations along the M4 between J23 Rogiet and J48 Pont Abraham.

The work will be undertaken during the night between 20:00 and 06:00 utilising mostly hard shoulder and lane closures; however, some total slip road closures will be required to provide the necessary safety zones in the below locations. 

Junction Closures

J23a EB On-Slip (Dates TBC) 

J23a EB Off-Slip (Dates TBC) 

J23a WB On-Slip (Dates TBC) 

J24 WB Off-Slip (Dates TBC) 

J28 EB Off-Slip (Dates TBC) 

J28 WB On-Slip (Dates TBC) 

J32 EB On-Slip (Dates TBC) 

J32 EB Off-Slip (Dates TBC) 

J33 WB On-Slip (Dates TBC)

Junction closures 

Phase 1 07/09/26 – 08/09/26 

J42 eastbound exit slip road 

J43 eastbound entry slip road 

Phase 3 08/09/26 – 09/09/26 

J41 westbound exit slip road 

Phase 5 10/09/26 – 18/09/26 

J38 eastbound entry slip road 

Phase 6a 20/09/26 – 23/09/26 

J38 eastbound entry slip road 

Phase 6b 23/09/26 – 28/09/26 

J38 westbound exit slip road

Junction Closures

Phase 1 07/09/26 – 14/09/26 

J36 eastbound entry slip road

Phase 2 15/09/26 – 08/10/26

J35 eastbound exit slip road

Signed diversions will be established on all slip road closures.

For further information, please contact Traffic Wales on 0300 123 1213 or via X and Facebook.