M4 Junction 32 Coryton Resurfacing Works

Start date: 7th of September 2026| End date: 12th of October 2026

Work to carry out essential carriageway resurfacing to a 1.54km section of M4 Junction 32 Coryton roundabout will commence on 07/09/2026 for 25 nights.

The work will be carried out over the 25 nights 20:00 – 06:00 under phased carriageway closures on M4 Junction 32 Coryton Roundabout. The works will be undertaken over 5 separate phases, outlined below:

Details of Restrictions

Start Date and Time**

End Date and Time**

Notes

 

Phase 1 – South Eastern Quadrant of Coryton Gyratory 

Inside and Lane 3 

 

20:00 07/09/2026

 

06:00 08/09/2026

 

Lane closures only, access maintained through Coryton Roundabout

 

Phase 2 – South Eastern Quadrant of Coryton Gyratory 

Outside and Lane 2

 

20:00 08/09/2026

06:00 09/09/2026

Lane closures on Coryton RAB

2 Way TTL with convoy system - Switch off

Closure of A470 NB Exit slip

Closure of A4054 Southbound only

Phase 3 – South of Coryton Gyratory 

Inside and Lane 3 (Including lay-by)

20:00

09/09/2026

06:00

10/09/2026

Lane closures only, access maintained through Coryton Roundabout

 

Phase 4 – South Western Quadrant of Coryton Gyratory 

Outside and Lane 2 

20:00

10/09/2026

06:00

11/09/2026

Diversion route provided on M4, turning traffic at M4 Junction 31

Phase 5 – South Western Quadrant of Coryton Gyratory 

Inside and Outside Lane

20:00

11/09/2026

06:00 

12/09/2026

Traffic for Asda and

Mcdonald deliveries to

be convoyed from

entrance point to

Longwood Drive

 

Traffic exiting Longwood

drive to be convoyed

through closure area.

Phase 6 – South of Coryton Gyratory 

Inside and Lane 2 (including access to Longwood Drive)

20:00

13/09/2026

06:00

14/09/2026

 

Phase 7 – North of Coryton Gyratory 

Inside Lane and Lane 2

20:00

14/09/2026

06:00

15/09/2026

Alternative access routes will be via a diversion through Tongwynlais 

Phase 8 – North of Coryton Gyratory 

Outside Lane (including A4054 Lane)

20:00

15/09/2026

06:00

16/09/2026

Alternative access routes will be via a diversion through Tongwynlais

Phase 9 – North Eastern Quadrant of Coryton Gyratory 

Inside and Lane 2 

20:00

16/09/2026

06:00

17/09/2026

Alternative access routes will be via a diversion through Tongwynlais

Phase 10 – North Western Quadrant of Coryton Gyratory 

Outside Lane and M4 EB On-Slip and A470 SB Off-slip 

20:00

17/09/2026

06:00

18/09/2026

Alternative access routes will be via a diversion through Tongwynlais

Phase 11 – East of Coryton Gyratory

Inside and Lane 2 

20:00

21/09/2026

06:00

22/09/2026

Alternative access routes will be via a diversion through Tongwynlais

Phase 12 – East of Coryton Gyratory 

Outside Lane to A470 SB On-slip and A470 NB cut through 

20:00

22/09/2026

06:00

23/09/2026

Alternative access routes will be via a diversion through Tongwynlais

Phase 13 – East of Coryton Gyratory 

M4 WB Off-slip including Outside Lane to A470 SB on-slip

20:00

23/09/2026

06:00

24/09/2026

Alternative access routes will be via a diversion through Tongwynlais

Phase 14 – North Western Quandrant 

Outside Lane and A470 NB On-Slip Dedicated lane

20:00

24/09/2026

06:00

25/09/2026

Closure of A470 NB ENTRY & M4 EB EXIT with 2 way temporary traffic signals 

convoy working

Switch off of existing signals

 

Phase 15 - North Western Quandrant

Inside, Lane 2 and A470 NB On-slip

20:00

25/09/2026

06:00

26/09/2026

Closure of A470 NB ENTRY & M4 EB EXIT with 2 way temporary traffic signals 

convoy working

Switch off of existing signals

 

High Friction Surfacing:

 

20:00

28/09/2026

06:00

12/10/2026

 

** dates provisional, may be subject to change

 

Access to residential areas and business premises off the adjacent county side roads has been considered and is planned for each as follows:

· Merthyr Road and Oldfield Road – during Phases 2 and 3, alternative access route will be via diversion through Tongwynlais.

· A4054 Pendwyallt Road – during part of Phase 1, alternative access route from south via diversion from Gabalfa Interchange.

· Longwood Drive – as no alternative access is available, access into and out of Longwood Drive will be maintained throughout the programme except for shift #6 (planned for Sunday 13/09/26) when the gyratory outer lanes across Longwood Drive will be resurfaced. Only emergency access to Longwood Drive will be available during this shift.

For further information, please contact Traffic Wales on 0300 123 1213 or via Twitter @TrafficWalesS