A477 Llanteg Pedestrian Crossing

Start Date: 20/10/25 | End Date: 12/12/25

Work to install new pedestrian refuge on A477 in Llanteg will commence on 20/10/2025 for 7 weeks.

Work to install new pedestrian refuge to assist pedestrians crossing the main A477 trunk road.

The work will be carried out over 4 phases:

Phase 1 

A477 and Taverspite Junction 20 October to 7 November – Works off trunk road and in county road junction with intermittent Stop/Go traffic control to allow access to the site 

Phase 2 

Eastbound 9 November to 24 November– Lane closure with 24hr traffic lights which will be manned during working hours.

Phase 3 

Westbound 25 November to 11 December– Lane closure with 24hr traffic lights which will be manned during working hours, access to the petrol filling station will be maintained.

Phase 4 

Resurfacing main carriageway both directions 9 December to 12 December, This phase of works will be undertaken over night between 18:00 and 06:00.