Start date: 28/02/26 - End date: 05/03/26
A55 J19 East and West – Essential carriageway Resurfacing works 28/02/26 – 05/03/26 between 19:00 – 06:00.
Work to carry out essential carriageway repairs of the A55 J19 East and West will commence on 28/02/2026 for 5 nights.
28/02 – 02/03: J19 westbound off‑slip closed
03/03 – 04/03: Full eastbound closure at J18 and westbound closure between J19 on/off slips
01/03 – J19 westbound off‑slip will remain closed during the day to allow the surface to cure.
The programmed work will be carried out over 5 nights 19:00 – 06:00 under full slip and carriageway Road closures. Signed diversion route will be implemented and will utilise the A547 and A55.
The works are being carried out overnight when traffic flows are historically lower to minimise disruption.
For further information, please contact Traffic Wales on 0300 123 1213 or via X @TrafficWalesN