Start date: 27/04/26 End date: 16/06/26
The first phase of works on the A40 from the junction at Castle Road to the zebra crossing by the Crickhowell Fire Station was successfully delivered in early 2025. The second phase of works on the A40 extends from the zebra crossing by the Crickhowell Fire Station to the access for the Asda petrol station. Works are planned to be undertaken between Monday 27th April and Friday 19th June 2026. These essential resurfacing and improvement works are necessary to address areas of deterioration and failure, providing a smoother/safer running surface for road users, as well as improvements to drainage and pedestrian infrastructure.
Due to the complexity of delivering the work, varying traffic management arrangements will be required throughout the programme. A detailed breakdown of the proposed restrictions and programme is provided below:
Details of Restrictions | Start Date and Time** | End Date and Time** | Notes |
A40, from the junction with High Street to the junction at Greenhill Way: Night time full closure when traffic flows are lower. | 13/07/2026 19:00 | 17/07/2026 07:00 | Nighttime works only between 19:00 to 07:00 Monday to Thursday.
|
A40 at the junction with Brynant Road. Night time works under temporary traffic lights. | 13/07/2026 19:00 | 17/07/2026 07:00 | Nighttime works only between 19:00 to 07:00 Monday to Thursday.
|
** dates provisional, may be subject to change
For further information, please contact Traffic Wales on 0300 123 1213 or via Twitter @TrafficWalesN