Start Date: 04/11/2024 | End Date: 14/12/24
Essential works to address hazardous trees adjacent to the A465 trunk road between Llandarcy and Aberdulais will commence on 04/11/2024 for 6 weeks (Monday to Friday working only).
The work will be undertaken both during the day (09:30-15:30) and during the night (20:00-06:00) utilising mostly lane and hard shoulder closures.
Some night-time total slip road closures will be required during the programme of works, to provide the necessary safety zones.
Signed diversions will be put in place during total closures.
4-6 November
- Aberdulais southbound exit slip road will be closed overnight 20:00-06:00.
6-13 November
- Aberdulais southbound entry slip road will be closedovernight 20:00-06:00.
** Please note, programme may be subject to change.
Aberdulais Southbound Exit Slip Road Diversion
Traffic exiting the A465 at Aberdulais via the southbound exit slip road, will instead continue southbound on the A465 and exit via the southbound exit slip road at Neath. There, traffic will navigate the Neath Interchange and join the A465 northbound carriageway via the A465 northbound entry slip road. Traffic will then travel northbound and exit the A465 at Aberdulais via the A465 northbound exit slip road.
Aberdulais Southbound Entry Slip Road Diversion
Traffic joining the A465 at Aberdulais via the southbound entry slip road, will instead navigate the Aberdulais gyratory and enter the A465 northbound carriageway via the A465 northbound entry slip road. Traffic will then travel northbound to Resolven and navigate the Resolven gyratory to return southbound on the A465 to Aberdulais.
For further information, please contact Traffic Wales on 0300 123 1213 or via X @TrafficWalesS and Facebook @TrafficWalesS.