Start Date:25/03/2024 | End Date:22/05/2024
Work to carry out pedestrian crossing improvements in the vicinity of Cilycwn Road and Stone Street. The works includes localised carriageway resurfacing, footway resurfacing, and the installation of a signalised pedestrian crossing. Works will commence on 25/03/2024 and conclude on 22/05/2024.
The work will be carried out over 39 days between 8:00 – 17:30 and 9:30 – 15:30 under single lane closures in both directions on the A483 New Road/ Llanfair Road section in Llandovery.
2 April (8:00) – 12 April (17:30) & 15 April – 16 April
• Lane closures southbound
16 April (9:30) – 14 May (15:30) & 14 May – 22 May
• Lane closures northbound
** Please note, programme may be subject to change. Updates will be provided.
N/A
For more information, contact Traffic Wales on 0300 123 1213 or via X @TrafficCymruD and Facebook @TrafficWalesS