Start Date: 11/03/25 | End Date: 20/05/25
Work to carry out essential carriageway resurfacing to the A40 Hardwick roundabout, associated gyratory and connecting trunk roads will commence on 25/02/2025.
The work will be carried out overnight between the hours of 20:00 – 06:00 (excluding weekends) under a full carriageway closure for the A40 Monmouth Road Abergavenny, the A465 Abergavenny Eastern Bypass, A465 Heads of the Valleys Road, the A40 Raglan Road, the A4042 Pontypool Road and the A40 Hardwick Roundabout and associated gyratory in separate phases.
Heads of the Valleys Road Phase
11/03/25 (20:00) – 20/03/25 (06:00)
A465 Heads of the Valleys Road (Eastbound)
24/03/25 (20:00) – 04/04/25 (06:00)
A465 Heads of the Valleys Road (Westbound)
Heads of The Valleys Road Phase
Eastbound diversion:
Westbound diversion: