Start date : 27/01/2025 | End date : 06/02/2025
Work to carry out essential carriageway resurfacing to a 1.1km section of the A470 carriageway in Llanrwst between the Meadow Vale lay-by and Pont Fawr will commence on 27 January 2025 for approximately 3 weeks.
The work will be carried out under traffic signals with a convoy system leading traffic through the site.
The first phase of works (27/01/2025 – 06/02/2025 dependent upon progress of scheme) will be carried out during the daytime, whilst the second phase of works (06/02/2025 – 18/02/2025) will be carried out as a combination of daytime and evening works (approximately 17:00 – 02:00) when traffic flows are historically lower to minimise disruption.
All Abnormal loads over 3.0m are prohibited from travelling through the worksite.
No diversion in place.